PROJECT: Hung Dorm Elevator Upgrade Project.
LOCATION: Hung Dorm
DURATION:
In coordination with the students' daily routines and the school calendar, the construction will be carried out in two phases.
| Estimated Construction Dates | Estimated Activation Dates |
First Elevator | July 14 to August 30, 2024 | September 7, 2024 |
Second Elevator | September 8 to October 21, 2024 | October 30, 2024 |
Construction Hours:
Daily From 8:30 AM to 8:00 PM, with low-volume work after 5:00 PM whenever possible.
Construction Contractor: TAIWAN MITSUBISHI ELECTRIC.
Contact:
Division of Construction & Maintenance Tel: 03-5719169
Division of Student Housing Tel: 03-5715416
During the construction period, there will be noise in the construction area. Please be mindful of your safety when passing through the construction zone. We appreciate your understanding and cooperation.